Lamu Port Operationalization Secretariat

Overall Completion : 33.33 %

Projects Key Actions Activities
0 0 3

Status

Completed Ongoing Terminated Overdue
1 2 0 0

Project Key Action Activity Name Action Person Percent Completed Cost Start Date End Date Status Remarks Extension End Date Extension Reason
Commissioning date for Berth of Lamu Port Commissioning date for 1st berth of Lamu Port Work on daily basis, appraise the status to ensure timelines are met 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Committee has convened meetings including with the CS-The national Treasury 1/1/0001 12:00:00 AM
Commissioning date for Berth of Lamu Port Commissioning date for 1st berth of Lamu Port Prepare a dashboard of pending activities for easy tracking 0 0 1/4/2021 12:00:00 AM 5/4/2021 12:00:00 AM Completed Done by the Ad-Hoc Committee 1/1/0001 12:00:00 AM
Commissioning date for Berth of Lamu Port Commissioning date for 1st berth of Lamu Port Prepare Port Operation Strategy which should include Marketing Strategy 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Committee for Marketing and Promotion strategy formed. Members appointed from KPA, KRC, KeNHA and LCDA 1/1/0001 12:00:00 AM