Multi Agencies

Overall Completion : 12.5 %

Projects Key Actions Activities
14 15 16

Status

Completed Ongoing Terminated Overdue
2 14 0 0

Project Key Action Activity Name Action Person Percent Completed Cost Start Date End Date Status Remarks Extension End Date Extension Reason
Housing units/Accommodation Housing units/Accommodation Provide housing units/accommodation to your staff involved in the port operation 0 0 1/4/2021 12:00:00 AM 4/27/2021 12:00:00 AM Completed Under planning 1/1/0001 12:00:00 AM
Installation of Railway lines at Lamu Port Installation of Railway lines at Lamu Port Install the railway lines for internal evacuation of cargo at the Lamu Port 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing This is a media-term engagement (KRC, KPA) 1/1/0001 12:00:00 AM
Comparative Analysis of Operational Efficiency Comparative Analysis of Operational Efficiency Evaluate cargo shipping routes and time from the cargo sources to Djibouti and Port of Lamu 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing To be incorporated in the ToR 1/1/0001 12:00:00 AM
Comparative Analysis of Operational Efficiency Comparative Analysis of Operational Efficiency Undertake a comparative analysis of costs of transport goods from Lamu to Southern Ethiopia vis a vis Djibouti to southern Ethiopia 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Task assigned to Marketing Committee (LCDA and KRC) 1/1/0001 12:00:00 AM
Harmonization of implementation of LAPSSET Corridor Program Harmonization of implementation of LAPSSET Corridor Program Establish ways to ensure harmonized implementation of the LAPSSET Corridor Program with Partner States 0 0 5/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing LCDA to Coordinate and report 1/1/0001 12:00:00 AM
Planned Industrialization Planned Industrialization Partner States engage in identifying complementary Industrial Parks 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Task to be executed by the Marketing Committee (LCDA & SEZA) 1/1/0001 12:00:00 AM
Resource mobilization for the LAPSSET Corridor components Resource mobilization for the LAPSSET Corridor components Establish measures for resource mobilization for implementation of the program through PPP framework 0 0 1/4/2021 12:00:00 AM 4/27/2021 12:00:00 AM Completed Meeting convened. Outcome to be reported by The National Treasury (KPA and PPP Directorate) 1/1/0001 12:00:00 AM
Resource mobilization for the LAPSSET Corridor components Resource mobilization for the LAPSSET Corridor components Constitute a Sub-committee to work on resource mobilization for implementation of the LAPSSET Corridor components through PPP framework 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Meeting convened. Outcome to be reported by The National Treasury (LCDA and PPP Directorate) 1/1/0001 12:00:00 AM
Planning for Lamu Port City Planning for Lamu Port City LCDA to work with the Lamu County Government to develop a Detail Master Plan for the Lamu Port City 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Take it up with the Director of Physical Planning in Lamu on this issue 1/1/0001 12:00:00 AM
Settlement of Project Affected Persons (PAPs) Settlement of Project Affected Persons (PAPs) Establish ways on how to resettle persons displaced by the projects 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing 1/1/0001 12:00:00 AM
Land Acquisition and compensation Land Acquisition and compensation Facilitate land acquisition in Lamu for LAPSSET Corridor Program 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing To be informed by the Survey and route alignment (NLC; LCDA) 1/1/0001 12:00:00 AM
Land Acquisition and compensation Land Acquisition and compensation Establish how to undertake collective compensation of community land in Garissa through County Government 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Engage the county Government (LCDA and NLC) 1/1/0001 12:00:00 AM
Land Acquisition and compensation Land Acquisition and compensation Establish the correct position in respect to the amendment to the land act to allow for public to be undertaken even when land issues are being resolved 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Legal department to review the correct position 1/1/0001 12:00:00 AM
Community participation and acceptance of the projects Community participation and acceptance of the projects use local labour during project implementation as a benefit local community 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing To be Done (TBD) 1/1/0001 12:00:00 AM
Community participation and acceptance of the projects Community participation and acceptance of the projects Undertake the development of Corporate Social Responsibility Projects 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing continuous 1/1/0001 12:00:00 AM
Special Economic Zones Special Economic Zones Conclude tasks under the Transaction Advisory grant from AfDB to have Lamu SEZ gazetted 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing LCDA working on the matter (LCDA; SEZA) 1/1/0001 12:00:00 AM