All Partner Government Agencies

Overall Completion : 0 %

Projects Key Actions Activities
6 5 7

Status

Completed Ongoing Terminated Overdue
0 7 0 0

Project Key Action Activity Name Action Person Percent Completed Cost Start Date End Date Status Remarks Extension End Date Extension Reason
Commissioning date for Berth of Lamu Port Commissioning date for 1st berth of Lamu Port Finalize the preparations for operationlization of the port: Deploy officers to Lamu port by Agencies: Furnish and Equip offices for Agencies Staff and Undertake cabling 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Being done through the Ad-Hoc Committee 1/1/0001 12:00:00 AM
Off-take Route Options for the Lamu Port Off-take Route Options for the Lamu Port Work with Lamu County Government on development of rest stations and parking lots in Lamu 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing KeNHA to report (Address issues of site; Designs and location) 1/1/0001 12:00:00 AM
Marketing the use of LAPSSET Corridor Marketing the use of the LAPSSET Corridor Undertake marketing of the use of the LAPSSET Corridor with the Partner States 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Task to be executed by the Marketing committee and the Ministerial delegation (LCDA, KPA, KRC, KeNHA) 1/1/0001 12:00:00 AM
Marketing the use of LAPSSET Corridor Marketing the use of the LAPSSET Corridor Organize a Ministerial delegation to market the Lamu Port to Ethiopian counterparts 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing Letter done to the PS - State Department of Regional Development requesting the Ministry to take lead 1/1/0001 12:00:00 AM
Population Increase in Lamu Population Increase in Lamu Initiate planning for health services and waste management due impending population surge and planned operation of Lamu Port 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Directorate of Utilities to engage the County Government 1/1/0001 12:00:00 AM
Cess to Contractors Cess to Contractors Consider signing of agreement on management of cess during development of roads in the county 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing KeNHA and Garissa County Government 1/1/0001 12:00:00 AM
Update of the Crude Oil Pipeline Update of the crude Oil Pipeline Hold a joint meeting between the Ministry of Petroleum & Mining, KPC and LCDA to discuss the development of the crude oil pipeline and consider bringing its management under KPC 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Letter to PS and MD on the matter (LCDA, KPC and State Department of Petroleum) 1/1/0001 12:00:00 AM