Kenya Revenue Authority
Overall Completion : 50 %
Projects | Key Actions | Activities |
1 | 1 | 2 |
Status
Completed | Ongoing | Terminated | Overdue |
1 | 1 | 0 | 0 |
Project | Key Action | Activity Name | Action Person | Percent Completed | Cost | Start Date | End Date | Status | Remarks | Extension End Date | Extension Reason |
Updates on Custom and Logistics Support at Moyale OSBP | Updates on Custom and Logistics Support at Moyale OSBP | Dispatch a team from KRA to support and facilitate the KPA team understanding on minimum requirement for a Custom Area (Fencing) | 0 | 0 | 1/4/2021 12:00:00 AM | 4/27/2021 12:00:00 AM | Completed | Officers deployed | 1/1/0001 12:00:00 AM | ||
Nanyuki Inland Container Depot | Nanyuki Inland Container Depot | Gazette Nanyuki depot as a customs area | 0 | 0 | 1/4/2021 12:00:00 AM | 6/30/2021 12:00:00 AM | Ongoing | KRC engage KRA to have the area gazetted | 1/1/0001 12:00:00 AM |