Off-take Route Options for the Lamu Port |
Off-take Route Options for the Lamu Port |
Complete the construction of the remaining 6km of road of Lamu-Garsen Road |
|
0 |
0 |
1/4/2021 12:00:00 AM |
6/30/2021 12:00:00 AM |
Ongoing |
Works to be completed by June |
1/1/0001 12:00:00 AM |
|
Off-take Route Options for the Lamu Port |
Off-take Route Options for the Lamu Port |
Complete the installation of 8 culverts on Bura-Madogo Section of Road |
|
0 |
0 |
1/4/2021 12:00:00 AM |
6/30/2021 12:00:00 AM |
Ongoing |
Works to be completed by June |
1/1/0001 12:00:00 AM |
|
Off-take Route Options for the Lamu Port |
Off-take Route Options for the Lamu Port |
Begin clearance of 200m wide LAPSSET Corridor and undertake construction of a section for commissioning by H.E |
|
0 |
0 |
1/4/2021 12:00:00 AM |
5/31/2021 12:00:00 AM |
Ongoing |
The tarmacked section to be ready by time of the Port Commissioning |
1/1/0001 12:00:00 AM |
|