Kenya National Highways Authority

Overall Completion : 0 %

Projects Key Actions Activities
0 0 3

Status

Completed Ongoing Terminated Overdue
0 3 0 0

Project Key Action Activity Name Action Person Percent Completed Cost Start Date End Date Status Remarks Extension End Date Extension Reason
Off-take Route Options for the Lamu Port Off-take Route Options for the Lamu Port Complete the construction of the remaining 6km of road of Lamu-Garsen Road 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Works to be completed by June 1/1/0001 12:00:00 AM
Off-take Route Options for the Lamu Port Off-take Route Options for the Lamu Port Complete the installation of 8 culverts on Bura-Madogo Section of Road 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing Works to be completed by June 1/1/0001 12:00:00 AM
Off-take Route Options for the Lamu Port Off-take Route Options for the Lamu Port Begin clearance of 200m wide LAPSSET Corridor and undertake construction of a section for commissioning by H.E 0 0 1/4/2021 12:00:00 AM 5/31/2021 12:00:00 AM Ongoing The tarmacked section to be ready by time of the Port Commissioning 1/1/0001 12:00:00 AM