Kenya Railways Corporation

Overall Completion : 33.33 %

Projects Key Actions Activities
1 1 3

Status

Completed Ongoing Terminated Overdue
1 2 0 0

Project Key Action Activity Name Action Person Percent Completed Cost Start Date End Date Status Remarks Extension End Date Extension Reason
Cost Per Alternative Route Cost per Alternative Route Do market testing by using SGR from the Port of Mombasa to Nairobi, MGR from Nairobi to Nanyuki and Road to Moyale 0 0 1/4/2021 12:00:00 AM 6/30/2021 12:00:00 AM Ongoing KRC to report 1/1/0001 12:00:00 AM
Status of the LAPSSET Railway Status of the LAPSSET Obtain a status update on the commercial contract signed in 2017 to extend the SGR from Mariakani to Lamu 0 0 1/4/2021 12:00:00 AM 12/31/2021 12:00:00 AM Ongoing 1/1/0001 12:00:00 AM
Nanyuki Inland Container Depot Nanyuki Inland Container Depot Inspect the Nanyuki stacking yard for preparedness 0 0 1/4/2021 12:00:00 AM 4/30/2021 12:00:00 AM Completed KRC to undertake this on Friday 3oth April 2021 1/1/0001 12:00:00 AM